The observatory at Montreal’s Olympic Stadium has been closed to the public for years due to construction delays. A $1 million lawsuit alleges that poorly designed windows have contributed to the delays.
Allegedly, the glass supplied and installed at the site is affected by optical distortion, making it unfit for its intended purpose.
The Olympic Park is seeking $1.02 million from three companies linked to the project that it believes are responsible for the defect: Pomerleau, Lemay CO and Vitreco.
All three companies have reportedly refused to accept responsibility for the alleged error.
CityNews reached out to the Olympic Park officials but they declined to comment at this time.
The observatory has been closed to the public since 2020. Its reopening was initially scheduled for sometime between autumn 2023 and spring 2024, but it is now expected to reopen in spring 2027.
Officials say the project’s cost has also increased, rising from $81 million to $122 million.